Construction Information

UTA and UDOT are starting utility work on the Provo Orem Transportation Improvement Project (TRIP) on Thursday, July 28. This pre-construction phase consists of utility work and property acquisition which must take place prior to larger components of TRIP construction. Work includes relocating overhead power lines, water and gas lines, fire hydrants, water meters, traffic signals, street lights and storm drains. To accommodate utility work, some curb, gutter and asphalt will be removed. It will also be necessary to remove the trees in the center of University Parkway between University Avenue and Carterville Road. Once the project is completed, three times as many trees will be planted in their place.

UTA, UDOT and Utah Valley Transit Constructors are committed to maintaining safe driving conditions, keeping accesses open and keeping the public informed about construction. For safety, drivers should pay attention to shifting traffic lanes and follow flaggers' (traffic control personnel) directions. A 24-hour hotline is available to the public resolve construction issues and concerns: 1-888-661-8806.

3/17/17 Construction Update

Construction Progress In This Segment


Retaining wall construction on 400 W. in Orem.

Telecommunications/gas/power/water line relocations, storm drain installation and retaining wall construction are underway on the south side of the road between 400 W. and Main Street. Next week, crews will begin placing and grading road base west of 400 W.

Traffic Impacts:

  • Traffic has been shifted to the roadway center. Drivers are advised to reduce speeds and watch for lane shifts.
  • Left-turns are permitted only at signalized intersections. Left-turns are not permitted in mid-block sections over solid double yellow lines. Please be safe and make left-turns into businesses only at traffic lights.
  • Business accesses are being maintained. On-street parking has been eliminated.
  • Sidewalk is closed in the work zone on the south side of the road and pedestrian traffic is detoured to the north side.

Here is some additional detour information for the College Connector Trail and the Provo River Parkway Trail.


Phase One - Summer 2016 to Fall 2016

North of 2330 North, traffic will be shifted to the inside lanes to accommodate construction on the outside





South of 2330 North, traffic will be shifted to the outside lanes to accommodate construction in the center. Access to businesses will be maintained throughout.





BRIDGE CONSTRUCTION: Provo River Bridge
Summer 2016 - Summer 2017

To maintain traffic across the Provo River bridges, construction will take place in two phases.



During the first phase, traffic will be shifted to the outside so that the inside edge of the bridges can be removed to accommodate the construction of the center portion of the new bridges.



During the second phase, traffic will be shifted to the inside onto the new center bridge section. This will allow us to remove the remaining portions of the bridges and complete the construction of the outer portion of the new bridges.

PHASE 2: 800 East to University Ave
Fall 2016 - Summer 2017

North of 2330 North, traffic will be shifted to the outside lanes to accommodate construction in the center.

South of 2330 North, traffic will be shifted to the center lanes to accommodate construction on the outside.

Access to businesses will be maintained throughout.



South of 2330 North, traffic will be shifted to the center to accommodate construction on the outside.




FINISHED PRODUCT

When the new bridge and roadway are complete, there will be three traffic lanes in each direction and room for the BRT in the middle. The College Connector bike route will provide bike access throughout this area.