Utah Valley University (UVU) Campus

11/9/2018 Construction Update

Construction Progress In This Segment


UVU Station.

UVX station platform work is ongoing at the UVU Station on College Drive, which is UVX serviceable.

University Parkway Orem (400 West - 800 East)

11/9/18 Construction Update

Construction Progress In This Segment


University Place Station

Ongoing Work

  • UVX station platforms at the Lakeview (400 W.), Main Street and University Place (750 E.) stations
  • Remaining curb, driveway, sidewalk, irrigation, landscaping and lighting installations
  • Installation of permanent lane striping, symbols and signage
  • Finish work at 200 E. and 800 E

Roadway smoothness grinding is expected to begin next week along the corridor.

Traffic Impacts

  • Intermittent night-time lane restrictions are effective in segments along Univ. Pkwy between Univ. Ave. in Provo and 400 W. in Orem for installation of permanent lane striping and symbols. Restrictions are effective Sunday through Thursday nights between 9 p.m. and 6 a.m. Motorists should expect delays and are advised to use alternate routes.
  • Motorists are advised to reduce speeds and watch for lane shifts. Left-turns are permitted only at signalized intersections. Left-turns are not permitted in mid-block sections. Please be safe and make left-turns into businesses only at traffic lights.

University Parkway Diagonal (800 East, Orem - University Avenue, Provo)

11/9/18 Construction Update

Construction Progress In This Segment


550 West Station

Installation of permanent lane striping, symbols and signage continues along the corridor, with intermittent night-time lane restrictions in work zones.

Platform work continues at the 550 West Station. Finish work continues at Freedom Blvd.

Traffic Impacts

  • Intermittent night-time lane restrictions are effective in segments along Univ. Pkwy between Univ. Ave. in Provo and 400 W. in Orem for installation of permanent lane striping and symbols. Restrictions are effective Sunday through Thursday nights between 9 p.m. and 6 a.m.

Trail Impacts

  • The College Connector Trail is closed along the Univ. Pkwy diagonal between 800 E. and 2230 N. to facilitate roadway widening work at the top of the diagonal and barrier work on the river bridge Alternate routes are shown on the map below for both closures.

Brigham Young University (900 East)

11/9/2018 Construction Update



900 East, Provo

Sidewalk construction continues on northbound 900 E. between Cedar Ave. and Fir Ave. and southbound 900 E. from Campus Lane to 900 N.

Traffic Impacts

  • Lane restrictions are effective on northbound 900 E. between Cedar Ave. and Fir Ave. and southbound 900 E. between Campus Lane and 900 N. Sidewalk detours are in place.

700 North Provo (700 North - 500 South)

11/9/18 Construction Update


Joaquin Station

UVX station platform work is ongoing at the Joaquin Station (400 E.), which is UVX serviceable.

Traffic Impacts

  • With median curbing installed along the center of 700 N., north/south thru-traffic is permitted only at the 200 E. and 400 E. intersections. Motorists should not use the pedestrian crosswalks between the center medians in order to cturn left or make a U-turn. Driving in between the median in pedestrian crosswalks is unsafe and illegal. Please obey all traffic laws while travelling through the area.
  • On-street parking is NOT permitted along 700 N. between Univ. Ave. and 700 E. Citations will be issued for vehicles parked in this zone.
  • Pedestrian access is being maintained at intersections. To maintain public safety, pedestrians and bicyclists are advised to stay out of the roadway work zone and remain on the sidewalk and walkways at intersections.

University Avenue Provo (700 North - 500 South)

11/9/18 Construction Update

Construction Progress In This Segment

 
Academy Square Station

Ride UVX for free to your favorite downtown shop or restaurant! University Avenue businesses are open and easily accessible, with plenty of public parking available.

UVX station work continues at the Academy Square (600 N.), 300 North, Center Street, and 400 South stations.

Median curb, lighting, irrigation, landscaping and brick paver installations continue along the corridor.

Reconstruction is underway on the east leg of the 200 S. intersection.

Permanent striping and signage installations continue.

Traffic Impacts

  • Intermittent night-time lane restrictions are effective in segments along Univ. Ave. between 750 N. and 500 S. for installation of permanent lane striping and symbols.Restrictions are effective Sunday through Thursday nights from 9 p.m. to 6 a.m.
  • The eastern leg of the Univ. Ave./500 N. intersection is closed to replace a temporary asphalt patch with concrete. Business access is maintained.
  • The eastern leg of the Univ. Ave./200 S. intersection is closed for reconstruction.
  • Intermittent daytime (10 a.m. – 2 p.m.) lane restrictions are effective on Univ. Ave. between 500 S. and 750 N. to accommodate median and shoulder work.

Provo Station/East Bay

11/9/2018 Construction Update


East Bay North Station 

UVX station platform work continues at the East Bay North Station.


Provo Towne Centre


Towne Centre Blvd. Station

UVX station platform work continues at the Towne Centre Blvd. Station.

Novell Place, Provo


East Bay South Station

UVX station platform work continues at the East Bay South Station.