3/24/17 Construction Update

Construction Progress In This Segment


Storm drain installation on 500 E. in Provo.

Storm drain installation is underway on 500 E. from 600 N. - 700 N. and 300 E. from 400 N. - 500 N. Work will begin by early next week on 700 N. from 500 E. to 700 E. Potholing operations (locating underground utilities) are underway along 700 N. and fiber companies are beginning to pull new fiber lines.

Traffic Impacts

  • For storm drain installation, sections are closed to thru-traffic and on-street parking is restricted in the work zone. Access is maintained for residents and service vehicles.
  • Pedestrian access is being maintained at intersections. To maintain public safety, pedestrians and bicyclists are asked to stay out of the roadway work zone and remain on the sidewalk and walkways at intersections.