Click here for overview of University Avenue construction.

Construction Information

Construction is scheduled for University Avenue between 700 North and 400 South from Winter 2017 to Spring 2017.

3/24/17 Construction Update

Construction Progress In This Segment

Section 5 Progress Update


Storm drain installation on Univ. Ave. in Provo. 

Beginning during the week of March 27, removals will begin along the west side of University Ave. between 500 S. and 200 S. in preparation for utility relocations and roadway widening. Median storm drain installation is underway on University Ave. between 400 N. and 800 N.

Preliminary signal work continues at 100 S. Underground boring is underway between 920 S. and 1200 S.

Traffic Impacts

  • For median storm drain work from 400 N. - 800 N., traffic is shifted to the outside lanes, on-street parking is restricted, the center turn lane is closed in the work zone and periodic left-turn lane closures are effective at intersections. Thru-traffic lanes remain open on University Ave. and cross-streets during the work. Business and pedestrian accesses are open.
  • For widening work from 200 S. - 500 S., southbound shoulder and on-street parking closures will be effective in the work zone. All thru-traffic lanes will remain open on University Ave. and business and pedestrian accesses will be maintained.
  • Intermittent shoulder and sidewalk closures are in place to facilitate preliminary signal work.